Day 25(Monday, 10 May)
As usual on Monday morning, tazkirah and morning talk...then I continued my job to key in data for MSR...
Day 26(Tuesday, 11 May)
today was my first time in transmission to go out from office...En Syed asked me to follow him to do LOS(Line of Sight) survey for new site at UIA and Indera Mahkota 1...MSR for both sites were already submitted to HQ...both sites need to be surveyed again because they were not sure whether the transmission link path between the new site and LOS site were not blocked...according to MSR both sites are 24 meter lamp pole...
UIA site
picture above I captured on skylift @ 24 meter...we can see Wisma Celcom tower but according to MSR the LOS is to Atabara tower(somewhere behind the hill)...since Atabara tower is blocked so we need to change the MSR...
Indera Mahkota 1 site
this picture also taken on skylift @ 24 meter...according to MSR, LOS is to Wisma Celcom...so this site has no problem...
In the afternoon, I continue on my assignment to key in data for MSR and before went home I stopped by En Syed table because I saw him using Path Loss software...so I asked him about the software...the software is use to calculate the path distance and azimuth between 2 sites...also the software is use to produce path data as to attach with MSR..we also can view the obstacle between both sites graphically...the height of the obstacle and tower are estimation but for a very long path distance or hilly area we need to use topomap to be precise...
Day 27(Wednesday, 12 May)
In the morning there were meeting with Huawei...the meeting was about the link that need to be ready for May target on air sites...other agenda was about status on new link upgrading...after the meeting I continued with MSR...
Day 28(Thursday, 13 May)
As I was heard in the NPID meeting before, this month(May) projects will be delayed even though the KPI to achieve is 32 sites...this is cause by no equipments delivered plus other region(Sarawak, Sabah and Eastern) need to wait for equipments from central(swapped - new equipments for central, used equipment for other region)...so as long as no new equipments delivered at central region, other region cannot proceed with installation...in other word, I just have to key in data for MSR for the whole day...
Day 29(Friday, 14 May)
As I said before no outdoor work can be done, so I just have to key in data for MSR and today finally I managed to finished the MSR of all 130 sites...